Quick Summary
A pop top installation for a campervan takes several working days, depending on roof type, van model and extras. The fitting typically runs across three days of stripping, sealing and trimming, followed by a curing period. Confirm your exact timeframe with a quote for your specific van.
- Vehicle make, model and roof dimensions all change how the cutting and reinforcement is done.
- A basic elevating roof is quicker than one with a scissor mechanism or integrated bed platform.
- Corrosion or previous repairs found after opening the roof add unpredictable time.
- Ask the workshop for lead time and fitting duration separately.
- Decide on solar panels and roof bars at quoting stage, not after the roof is fitted.
Table of Contents
- How Long Does Pop Top Installation Take?
- The Campervan Pop Top Fitting Process, Step by Step
- Preparing Your Van Before the Fitting Date
- Planning Your Build With Solar Panels and Roof Bars
- Frequently Asked Questions
How Long Does Pop Top Installation Take?
A pop top installation for a campervan takes several working days, depending on roof type, van model and extras. Timeframes for your specific build are best confirmed with a quote. The most accurate answer comes from a quote for your specific van.
The factors that actually change the schedule:
- Vehicle make and model. Roof dimensions, curvature and strengthening differ between a Ford Transit, a Volkswagen Transporter and a Mercedes Sprinter, so cutting and reinforcement is not a fixed job.
- Roof system and design. A basic elevating roof with simple canvas is quicker than one with a scissor mechanism, gas struts, a hard-shell top or an integrated bed platform. More moving parts mean more alignment and testing.
- Existing fittings and previous work. Roof racks, vents, skylights, aerials or earlier repairs must be removed or worked around, and corrosion found once the roof is opened adds unpredictable time.
- Custom work. Solar panels, roof bars, interior lighting, bed boards and bespoke trim add wiring, mounting and finishing stages. Decide these at quoting stage.
- Parts availability. An in-stock roof system can be fitted on the booked date; a made-to-order canvas or backordered mechanism can push the job back weeks.
- Workshop workload and season. Ask for lead time and fitting duration separately.
Our online configurator at T29 Customs gives you an instant, transparent quote before you commit, so you can see what your specific build involves.
The Campervan Pop Top Fitting Process, Step by Step
Confirm at quoting stage whether your estimate is workshop hours or calendar days.
A typical sequence looks like this:
Day one, strip, prepare and cut. The van is checked in, personal items removed, and the roof area masked and protected. The existing roof is opened along the marked line, and structural reinforcement or strengthening plates are added to the aperture. A standard low-roof panel van is quicker than a high-roof or one with existing roof furniture, and previous repairs or corrosion add time before cutting starts.
Day two, frame, canvas and sealing. The pop top frame and mechanism are trial-fitted, aligned and fixed. The canvas is fitted to the frame and aperture, and sealing is applied around the perimeter and fixings. Sealant needs time to cure before the roof is cycled or exposed to weather, so most installers will not hand the van back the same hour.
Day three, trim, electrics and checks. Interior trim is cut and refitted around the new aperture, roof lining and edging are finished, and any electrics are routed and tested. The roof is cycled through open and closed positions, checked for alignment and canvas tension, and the seals inspected.
Final stage, curing, inspection and collection. Depending on the sealant, the installer may ask you to leave the roof closed for a period, avoid a pressure wash for the first few days, and return for a follow-up check. Ask for these instructions in writing.

The article breaks the fitting into a sequence of days, with each stage adding time.
| Stage | What happens | Time note |
|---|---|---|
| Strip, prepare and cut | Van checked in, roof opened, aperture reinforced | Day one |
| Frame, canvas and sealing | Frame fitted, canvas and perimeter sealing applied | Day two |
| Trim, electrics and checks | Trim refitted, electrics tested, roof cycled | Day three |
| Curing, inspection and collection | Roof kept closed for a period, follow-up check | Final stage, after sealant cures |
Preparing Your Van Before the Fitting Date
Good preparation shortens the job and avoids delays. Clear all personal items and loose equipment, and check with the workshop what preparation your van needs before the fitting date. Our guide explains how to maintain pop top seals before and after fitting.
Plan drop-off and collection in advance, and confirm the fitting date and vehicle requirements with the workshop ahead of time.
Planning Your Build With Solar Panels and Roof Bars
Adding solar panels or roof bars changes both the installation time and the roof layout, so decide early.
If you plan to add solar, set this out at the quoting stage rather than after the roof is fitted. For a complete guide, see our article on campervan solar panel roof installation.
Frequently Asked Questions
How long does it take to install a pop-top roof on a campervan?
Timeframes depend on the vehicle, the roof system and the scope of the work. Ask T29 Customs for a timeframe based on your specific build when you request a quote through the online configurator. Booking details and lead times are best confirmed directly with the workshop before you plan your time off the road.
How long will my campervan be off the road during pop-top installation?
Ask about drop-off and collection arrangements when you book, so you can organise transport in advance. Confirm the expected schedule in writing before you commit to dates.
Can I drive my campervan straight after a pop-top roof is fitted?
Check with the installer at handover before driving the van away, and ask whether any aftercare steps apply to your build.